STAGE 4.1 DOCUMENTATION - CONSTRUCTION
CERTIFICATE
Objective: To prepare and coordinate information required
for the drawings needed for a Construction Certificate. To do this
we will;
|
EST TIMING
4 - 8 weeks
|
FEES
% of build cost
|
|
Review of DA conditions
|
Review and follow up conditions specified in the DA
approval.
Confirm any additional work (information, reports or drawings)
required by Council in the DA approval.
|
|
Confirm compliance of design with BCA.
|
|
Source fee proposals and arrange for client to engage the
Certifier.
|
|
Team meeting
|
Conduct a team meeting for all members to be appraised of issues
raised in DA approval.
Confirm the timetable for moving forward and work required for
the CC from various members.
|
|
Construction Certificate
|
Integrate work of consultants into our documentation.
|
|
Update and develop general arrangement plans, elevations and
sections at 1:100 scale.
|
|
Assumptions
|
Team members will work in a collaborative and cooperative way to
help deliver a timely and proficient service.
One meeting with client in our office to confirm final
documentation and sign forms.
|
|
Outcomes
|
- Complete Construction Certificate (CC)
submission
- Complete CC form
|
|
Additional fees
|
Co-ordination of the work and reports of
consultants
Co-ordination of the Certifier
Additional information, reports or drawings required as a
result of the DA approval
Any changes to the design initiated by the
client
|
Hourly rates
|